The existing Gas Boiler was installed in this area and first works was to move the Gas Boiler to a new location - new flue system - updated gas supply - updated heating pipe-work
Our second stage of works was to move and adapt the existing drainage allowing for all new services WC - Shower Tray and Basin waste. Floor repaired and made good - add floor insulation with new screeded floor.
Special care was taken with the new screeded floor to make sure all levels would guarantee that shower water would discharge into the shower gully.
Allow for electric underfloor heating and install new floor tiling. Construct new cupboard round the existing Boiler - install new WC frame system for wall hung WC
Shower Valve and wet room shower enclosure panels - Wall Hung WC - Wall Hung Basin - all new wall tiling with purpose made splashback over new basin unit - new Towel Warmer
Pictures below show the completed installation with new Quadrant Enclosure, new tiling, exciting WC and Cistern and shower room furniture:
We would like to thank the following Plumbing and Tiling suppliers in there help for suppling all the materials for the above design:
HPS Supplies Ltd: ANTHONY’S WAY, MEDWAY CITY ESTATE, ROCHESTER ME2 4DY
CAF Ceramics & Stone Ltd: BEDDOW WAY, AYLESFORD. ME207BT
Topps Tiles: KNIGHT ROAD, STROOD. ME2 2AQ
Get In Touch Today
If you would like more information or would like a free quote please get in touch.